Explosives - Show detonation

Before blasting with explosive substances (e.g. blasting buildings or blasting in the course of road construction work), the holder of the licence must notify the competent authority of the blasting in accordance with Section 7 of the Explosives Act. A change to a previously notified blasting operation must also be notified.

Procedure

1. submit a notification of blasting in accordance with § 1 or § 2 of the 3rd Explosives Ordinance. You can do this in writing by post (in duplicate), fax or e-mail to sprengstoff@lagetsi.berlin.de.
  • Blasting in facilities that are authorised in accordance with § 4 of the Federal Immission Control Act (e.g. in quarries) is exempt from the notification requirement. However, this only applies to blasting that is covered by the licence.

2. You will receive a confirmation of receipt. If there are any concerns, the authority will contact the person responsible.

Prerequisites

Documents required

  • Blasting notification according to § 1 or § 2 of the 3rd SprengV
    Submit the completed notification in writing by post (in duplicate), fax or e-mail to sprengstoff@lagetsi.berlin.de.
  • Calculation and planning documents:
    • Type, method and scope of blasting
    • the type and maximum quantity of explosives and detonators to be used for each blasting operation, and, when using time-detonators, the maximum quantity of explosives per detonation stage
    • the distance of the blasting sites from buildings and facilities requiring special protection, in particular hospitals, schools, old people's and children's homes, sports facilities and playgrounds within a radius of at least 1,000 metres
    • the safety measures, in particular the cover areas for employees, barriers along traffic routes and precautions to protect neighbouring homes and workplaces against flying stones, vibrations, blast clouds and noise
  • In individual cases: expert opinion
    If there are doubts about the documents and therefore about the planned building project, an expert opinion can be requested. The authority will inform you of this after receiving your notification.
  • If the notification does not specify the distance of the blasting site from the nearest traffic routes, residential and working areas and public supply facilities: Site plan (to scale)
    with an indication of the blasting sites, including their foreseeable changes in position and the distance from traffic routes, residential and working areas and public supply facilities within a radius of at least 300 metres

Fees

None

Average time to process request

6 - 8 weeks